Borealis restarts PDH construction site in Kallo with Ponticelli as contractor

  • Restart of construction works as of 3 October 2022, focused on the mechanical works and highly specialized piping of Borealis’ new Propane Dehydrogenation (PDH) plant in Kallo, Belgium
  • Thorough social controls have been set in place to respect and value the workers on site
  • Ponticelli and Borealis are committed to set a new standard for industrial construction works
  • Start-up expected during the second half of 2024

Following a standstill for 80% of the construction works in the Kallo PDH project, Borealis carried out a re-tendering process for the Mechanical and Piping construction works. After careful consideration, Borealis has now granted a majority of these works to the contractor Ponticelli. Works on the construction site will now further gradually increase as of 3 October 2022.

The prolonged standstill and gradual re-start of the project has consequences for the timeline of the project. Borealis expects start-up of the new PDH plant during the second half of 2024.

Borealis has zero tolerance for any malpractices. Borealis has implemented these measures to identify and address any potential lack of control by (sub)contractors:

  • All workers and (sub)contractors are informed and encouraged to make use of Borealis’ ethics hotline. This tool is accessible for Borealis workers and externals and allows for ethics-related concerns to be filed in 24 languages. In this way we can best early detect wrongdoings and take the required measures in the shortest timeframe
  • Borealis has reinforced its contractor auditing and vetting process to ensure that our contractors are effectively controlling their subcontractors.
  • To ensure further compliance, we ask each contractor and subcontractor to sign a formal binding declaration prior to deployment on the site in which they formally confirm to be fully compliant with applicable Belgian labour, social security and tax laws.

“We feel sorry for the workers employed by subcontractors for what has happened to them. Borealis has a zero tolerance policy regarding human rights violations, and we act accordingly. With the restart of the construction with Ponticelli, Borealis has further strengthened its standards for major expansion projects in a safe way,” comments Philippe Roodhooft, Borealis Executive Vice President. “Any contractor who does not comply with highest professional standards, be it directly or indirectly, disqualifies as a partner for us.”

“We are very grateful to Borealis for their confidence in these delicate times, which displayed our shared value to never compromise on our most important asset: our People,” comments Thierry Le Gangneux, CEO of Ponticelli. “And thanks to the reinforced connection between our Groups, we are more committed than ever to make this project a success.”

END

Media contacts:

Borealis

Virginia Wieser
Senior Manager, Corporate Communications,
Brand & Reputation
Borealis Communications Belgium

Anne Cornelissen
Expert Communications
T +43 1 22 400 772 (Vienna, Austria)
media@borealisgroup.com
tel.: +32 475 56 02 31 or + 32 11 45 90 66 (Belgium)
media.belgium@borealisgroup
Ponticelli

Bertrand Wyns
Hill+Knowlton Strategies

Bertrand.Wyns@hkstrategies.com
Downloads
221003 Kallo PDH project restart_EN English, Dutch, French, German
Media Contact
Group Media desk
Virginia Wieser, Lena Lehner
+43 1 22 400 899 (Vienna, Austria)
media@borealisgroup.com

Latest News

Media Release – 27/09/2023

Borealis appoints Britta Warnke Vice President Energy and Shanila Baseley Vice President Mobility and Advanced Products as of 1 September 2023

Read more

Media Release – 26/09/2023

Executive Vice President Lucrèce Foufopoulos-De Ridder to leave Borealis

Read more

Media Release – 18/09/2023

New Material Recovery Facility Opened in Banyuwangi Under Project STOP’s Expansion Program

Read more

News – 31/08/2023

All Borealis polyolefin and polyolefin compounding sites in Europe ISCC PLUS certified

Read more

Media Release – 04/08/2023

Project STOP Jembrana Hands Over the Program to the Local Government

Read more

Media Release – 14/07/2023

Borealis Scientific Innovation Award open for submissions

Read more

News – 13/07/2023

Borealis supports program to restore drinking water infrastructure in Beira, Mozambique after Cyclone Idai

Read more

Media Release – 11/07/2023

Borealis completes Stenungsund cracker furnace revamp, elevating plant to higher energy efficiency and process safety standards

Read more

Case Study – 05/07/2023

Borealis completes the sale of its nitrogen business to AGROFERT

Read more