Borealis restarts PDH construction site in Kallo with Ponticelli as contractor

  • Restart of construction works as of 3 October 2022, focused on the mechanical works and highly specialized piping of Borealis’ new Propane Dehydrogenation (PDH) plant in Kallo, Belgium
  • Thorough social controls have been set in place to respect and value the workers on site
  • Ponticelli and Borealis are committed to set a new standard for industrial construction works
  • Start-up expected during the second half of 2024

Following a standstill for 80% of the construction works in the Kallo PDH project, Borealis carried out a re-tendering process for the Mechanical and Piping construction works. After careful consideration, Borealis has now granted a majority of these works to the contractor Ponticelli. Works on the construction site will now further gradually increase as of 3 October 2022.

The prolonged standstill and gradual re-start of the project has consequences for the timeline of the project. Borealis expects start-up of the new PDH plant during the second half of 2024.

Borealis has zero tolerance for any malpractices. Borealis has implemented these measures to identify and address any potential lack of control by (sub)contractors:

  • All workers and (sub)contractors are informed and encouraged to make use of Borealis’ ethics hotline. This tool is accessible for Borealis workers and externals and allows for ethics-related concerns to be filed in 24 languages. In this way we can best early detect wrongdoings and take the required measures in the shortest timeframe
  • Borealis has reinforced its contractor auditing and vetting process to ensure that our contractors are effectively controlling their subcontractors.
  • To ensure further compliance, we ask each contractor and subcontractor to sign a formal binding declaration prior to deployment on the site in which they formally confirm to be fully compliant with applicable Belgian labour, social security and tax laws.

“We feel sorry for the workers employed by subcontractors for what has happened to them. Borealis has a zero tolerance policy regarding human rights violations, and we act accordingly. With the restart of the construction with Ponticelli, Borealis has further strengthened its standards for major expansion projects in a safe way,” comments Philippe Roodhooft, Borealis Executive Vice President. “Any contractor who does not comply with highest professional standards, be it directly or indirectly, disqualifies as a partner for us.”

“We are very grateful to Borealis for their confidence in these delicate times, which displayed our shared value to never compromise on our most important asset: our People,” comments Thierry Le Gangneux, CEO of Ponticelli. “And thanks to the reinforced connection between our Groups, we are more committed than ever to make this project a success.”

END

Media contacts:

Borealis

Virginia Wieser
Senior Manager, Corporate Communications,
Brand & Reputation
Borealis Communications Belgium

Anne Cornelissen
Expert Communications
T +43 1 22 400 772 (Vienna, Austria)
media@borealisgroup.com
tel.: +32 475 56 02 31 or + 32 11 45 90 66 (Belgium)
media.belgium@borealisgroup
Ponticelli

Bertrand Wyns
Hill+Knowlton Strategies

Bertrand.Wyns@hkstrategies.com
Downloads
221003 Kallo PDH project restart_EN English, Dutch, French, German
Media Contact
Group Media desk
Virginia Wieser, Lena Lehner
+43 1 22 400 899 (Vienna, Austria)
media@borealisgroup.com

Latest News

Media Release – 26/04/2024

​​OMV and Borealis sign long-term supply agreements with TOMRA for recycling feedstock produced from mixed waste​

Read more

News – 18/04/2024

Borealis and Borouge expand HVDC production capacity to meet the needs of the energy transition

Read more

Media Release – 09/04/2024

Borealis invests EUR 4.5 million in Porvoo steam cracker, enabling increased share of circular raw materials used in production

Read more

Media Release – 02/04/2024

Borealis further expands its advanced mechanical recycling capacity with closing the acquisition of Integra Plastics AD

Read more

Media Release – 28/03/2024

FDA clears Borealis’ Borcycle™ M recycled plastics for use in food-grade packaging

Read more

News – 27/03/2024

Update on the Kallo Case

Read more

Media Release – 26/03/2024

Borealis and AKVA group launch groundbreaking Polarcirkel™ workboat hull crafted from renewable feedstock-based plastic

Read more

News – 22/03/2024

Annual Report 2023 published

Read more

Media Release – 20/03/2024

Project STOP marks further major milestones in 2023 and makes significant progress in the Project STOP Banyuwangi Hijau expansion program

Read more