Back to News

About the Kallo Case

Borealis News

Update on Alleged Human Trafficking Practices by (Sub)contractor at Propane Dehydrogenation Construction Site in Kallo, Belgium

In 2019, Borealis started constructing a propane dehydrogenation (PDH) plant in Kallo, Belgium. This is a mega project, representing an investment of more than EUR 1 billion.

As Borealis produces chemicals, its core competence is not building new plants, nor does the Group have the manpower to do this. Borealis has therefore outsourced 99% of the work to specialist engineering and construction companies.

After extensively screening the available contractors that specialise in this line of work, Borealis chose, amongst others, to engage IREM. Given the size and complexity of the project, Borealis also engaged Tecnimont as an EPCm (Engineering, Procurement & Construction Manager) for overall management and communication with all contractors including IREM.

During the original project set-up, Borealis worked with around 20 significant contractors on the Kallo PDH site. On an average work day, up to 1,200 workers were on the site, the majority of which were contractors. Overall, about 1,000 of the workers were originally employed via the IREM companies and their subcontractors.

Borealis compensates its contractors based on unit rates for work done and not based on hourly rates for individual people working on the site, as is customary for these kinds of contracts. The contracts with Borealis’ contractors for the construction site in Kallo have payment terms that are fully in line with Western European standards.

The possibility of large scale social fraud at the PDH construction site in Belgium only became clear to Borealis after the Belgian authorities intervened in mid-July 2022. The real potential impact became clear even later, after particularly alarming reports in the press in relation to social fraud and the possibility of human trafficking.

In late July 2022, Belgian media started to report on alleged human trafficking practices conducted by the IREM group and their sub-contractors Anki Technologies and Raj Bhar Engineering at the Kallo site, involving exploitation, inadequate compensation, lack of social security and poor housing conditions. The media subsequently alleged that Borealis had been informed two months earlier about these large scale human trafficking practices.

Borealis’ internal checks have established that in May 2022, a Borealis employee was made aware for the first time of allegations of social malpractices in relation to one IREM worker and that this incident had been reported to the Social Inspectorate of Belgium. The Borealis employee obtained this information through a private social media channel and immediately took steps to validate the information.

Borealis’ Response

Borealis has zero tolerance for any malpractice and puts stringent measures in place to mitigate related risks. The Group feels deeply sorry for the victims who have suffered maltreatment and disrespect of their basic human rights and has offered – to the extent legally allowed – its financial aid to support the organisations in charge, to provide them with physical and mental health support, safe shelter, help gaining official work permits or, if they prefer, relocating them.

Upon becoming aware that the authorities were investigating, Borealis immediately offered support and provided all requested information to the authorities, in full transparency.

After being informed of the alleged human trafficking practices by the IREM group and its subcontractors, Borealis took the following immediate measures.

The Group established a Crisis management team led by the relevant Executive Board member Philippe Roodhooft, conducted thorough internal checks, launched audits and inspections of other contractors and took other actions to improve monitoring and speaking-up related to its contractors’ business conduct.

Borealis also encouraged both internal and external stakeholders to use the Borealis Ethics Hotline, through which victims can also submit their grievances. All reports received via this Hotline were handled with the utmost priority and in line with legal requirements.

Borealis immediately suspended and later terminated all contracts with the IREM group companies, due to their non-compliance with the fundamental principles of contract. Borealis then retendered the contracts. Given the size of the contracts that Borealis had to terminate, more than 1,000 workers were affected and were unable to continue their work at the Kallo construction site.

After careful consideration, Borealis awarded a major part of the remaining mechanical and piping works to the contractor Ponticelli and implemented thorough social controls at the Kallo construction site, to respect and value the workers there. Work on the construction site gradually increased from October 2022. The continuation of the project has allowed many workers to return to the site and will allow many more to return in the future, in strict compliance with legal requirements and in line with Western European standards.

Towards the end of 2022, Borealis awarded the remaining electrical and instrumentation construction works to Equans. At the same time, NAFTO was awarded further elements of the remaining mechanical and piping works.

Keeping Stakeholders Informed

Borealis regularly provides transparent information to its employees and external stakeholders about the occurrences at the Kallo PDH construction site. Since the beginning of the incident, Borealis’ employees have received regular updates through streamed live events hosted by the Borealis Executive Board, including live question and answer sessions, townhall meetings, briefing packages cascaded via line management and intranet news. External stakeholders have received information via media releases, media relations and direct information, for example through the sales and public affairs teams.

Actions Taken to Ensure Similar Incidents will not Happen Again

Based on the lessons learned, Borealis has strengthened, and will further strengthen, its processes and mitigation measures. After thorough analysis and consultation with subject matter experts and external consultants, Borealis has implemented the following improvements to set a new standard and prevent a similar incident from happening again.

  • Social Compliance Management: Borealis has created the new position of Group Social Compliance Manager, who reports directly to the Group Compliance & Ethics Officer. The new manager is responsible for monitoring the proper and legal business conduct of Borealis’ contractors and all other supply chain partners, alongside colleagues from the compliance, procurement and internal audit functions. In addition to the Group function, Borealis has recruited a local Social Compliance Manager in Kallo and plans to also install local social compliance cells in other locations and significant projects. The scope of their responsibilities includes, amongst others, audits, spot checks, investigations, due diligence and vetting, contract review and coordination with procurement, health, safety, security and environment, legal, and People & Culture.
  • Speak-up campaign: Borealis strengthened its speak-up campaign, to encourage reporting of suspected or witnessed misconduct. The campaign is specifically addressed to workers of contractors, who are invited to directly contact Borealis in case of such misconduct.
  • Reinforcing project management: Borealis has introduced a number of changes to further enhance the quality of its project management
  • Improvement of processes: the Group has further improved processes for vetting, due diligence and monitoring of supply chain partners, including enhanced due diligence requirements for contractors who assign personnel to Borealis’ sites.
  • Training: additional training has been provided and created awareness for internal project teams and contractors, to address the detected issues.

This publication is also available in Dutch and German language.

Previous related news:

Borealis News

Media Contact
Group Media Desk
+43 1 22 400 899 (Vienna, Austria)
media@borealisgroup.com

Related News

Media Release – 26/04/2024

​​OMV and Borealis sign long-term supply agreements with TOMRA for recycling feedstock produced from mixed waste​

Read more

News – 18/04/2024

Borealis and Borouge expand HVDC production capacity to meet the needs of the energy transition

Read more

Media Release – 09/04/2024

Borealis invests EUR 4.5 million in Porvoo steam cracker, enabling increased share of circular raw materials used in production

Read more

Media Release – 02/04/2024

Borealis further expands its advanced mechanical recycling capacity with closing the acquisition of Integra Plastics AD

Read more

Media Release – 28/03/2024

FDA clears Borealis’ Borcycle™ M recycled plastics for use in food-grade packaging

Read more

News – 27/03/2024

Update on the Kallo Case

Read more

Media Release – 26/03/2024

Borealis and AKVA group launch groundbreaking Polarcirkel™ workboat hull crafted from renewable feedstock-based plastic

Read more

News – 22/03/2024

Annual Report 2023 published

Read more

Media Release – 20/03/2024

Project STOP marks further major milestones in 2023 and makes significant progress in the Project STOP Banyuwangi Hijau expansion program

Read more